INTEGRATED SYSTEMATIC OF PLANNING AND CONTROL OF PRODUCTION BASED ON LOCATION AND LAST PLANNER SYSTEM USING BIM 4D AND AUTOMATED PROCESSES


PALAVRAS-CHAVES:

4D BIM. Lean Construction. Production planning. Production control. Location.


PÁGINAS: 205
GRANDE ÁREA: Engenharias
ÁREA: Engenharia Civil
RESUMO:

Production Planning and Control (PCP) is essential for maintaining a continuous flow of production. However, even with a defined PCP system, construction projects have intrinsic difficulties. In order to contribute in the solution of these difficulties, Building Information Modeling (BIM) and Lean Construction (CE) are two paradigms that are contributing to the management of construction sites, providing improvements to the PCP systems. In addition, recent evidence points to location-based production planning and control (LBP) as a methodology that best suits the construction sector. Therefore, the study aims to propose a systematic for the integration of Production Planning and Control based on location using BIM 4D and lean construction practices. To this end, the work was developed based on the strategy Design Science Research, divided into the following steps: (a) Literature review and understanding of the problem - aims to understand the study-related themes and their gaps; (b) Suggestion - diagnosis of the production planning and control process and initial proposal of the PCP system using 4D BIM supported by LC; (c) Development of the proposal - application of the systematic in two case studies for development and improvement of the artifact; and (d) Evaluation - effectiveness of the interaction between LBP, BIM functionalities focused on PCP and the principles of lean construction, evaluating aspects related to the use of technology and the system developed for implementation. The two case studies will be conducted in the city of Salvador - BA. The evaluation of the artifact will base on the following constructs: (a) Impact on the identification and evaluation of the progress of the work and the planning process; (b) transparency of the process; (c) ease of adoption; (d) Usefulness of the proposed systematic; and (e) Collaboration. Data for such assessment will derived from semi-structured interviews, participant observation and generated products. The expected results are related to the identification of new evidences of interactions between BIM and LC, the effectiveness of the BIM and LC practices proposed jointly in the study, increased adherence between what was planned and executed, and the development of collaboration among the study participants. Encouraging the participation of all involved and a well-defined system for the planning, monitoring and control of the progress of works with the aid of 4D BIM models.


MEMBROS DA BANCA:
Presidente - 2618348 - DAYANA BASTOS COSTA
Externo à Instituição - EDUARDO LUIS ISATTO
Interno - 1315606 - REYMARD SAVIO SAMPAIO DE MELO